Era Infra Engineering Ltd. v. New Delhi Municipal Council
Case brief
What is this about?
The Court extended the mandate of the Arbitral Tribunal by 9 months from the date of the order, noting that the respondent had no objection to the extension despite not admitting the petition's averments. The interim period was regularized, and the petition was disposed of.
What did the court decide?
Mandate of the Arbitral Tribunal extended by 9 months from today to make and publish the award.