M/S Global Buildwell v. Pushpa Jain
Case brief
What is this about?
The Court allowed an application for condonation of delay in re-filing a petition. The petition, filed under Section 29A of the Arbitration and Conciliation Act, 1996, sought a six-month extension for the Arbitral Tribunal to complete proceedings, and the Court granted the extension until 30.06.2024.
What did the court decide?
Extension of the mandate of the Arbitral Tribunal by six months till 30.06.2024; condonation of delay of 17 days; regularization of the period from 01.09.2023.