M/S Arkas Energy LLP v. M/S Inox Wind Limited
Case brief
What is this about?
Petition under Section 29A of the Arbitration and Conciliation Act, 1996 sought a six-month extension of the arbitral tribunal's mandate. With the award reserved after final arguments, the court found sufficient cause, granted six months from 12.06.2024 to make and publish the award, regularised the intervening period, and disposed of the petition.
What did the court decide?
Six months' extension of the arbitral tribunal's mandate from 12.06.2024; the period thereafter regularised.