The High Court of Delhi, under Section 29A of the Arbitration and Conciliation Act, 1996, extended the mandate of an Arbitral Tribunal for three months upon the respondent's consent and undertaking to clear pending fees.
What did the court decide?
The mandate of the Arbitral Tribunal is extended for a further period of three months.