Gtl Infrastructure Ltd. v. Atc Telecom Infrastructure Pvt. Ltd.
Case brief
What is this about?
In an OR under Section 29A of the Arbitration Act, the Delhi High Court, with parties' consent, extended the arbitral tribunal's mandate for six months from February 29, 2024, as proceedings were at final arguments.
What did the court decide?
Mandate of the learned Arbitral Tribunal extended for six months with effect from 29.02.2024.