M/S Chaudhary Builders v. Union of India & Anr.
Case brief
What is this about?
Railway contractor sought appointment of an arbitrator under Section 11 of the Arbitration and Conciliation Act; Union opposed citing measurement book endorsements and an addendum as accord and satisfaction. The Court found no unambiguous final settlement certificate, held arbitrability questions are for the tribunal absent ex facie bar, and referred the disputes to arbitration under DIAC.
What did the court decide?
Delay in refiling condoned; petition allowed; disputes referred to arbitration under DIAC, arbitrator to be nominated from its panel.