National Highways Authority of India through Project Director v. M/S. Progressive Construction Ltd. through Authorised Representative
Case brief
What is this about?
In an application under Section 29A(4) of the Arbitration Act, the Delhi High Court extended the arbitrator's mandate by three months for passing the final award in a dispute between NHAI and Progressive Construction Ltd., referencing a similar extension granted in a connected petition.
What did the court decide?
Extension of the Arbitrator's mandate by three months from 26th February, 2024 with effect from that date.