M/S Harcharan Dass Gupta v. Azad Hind Coop Group Housing Society Ltd.
Case brief
What is this about?
114/2017 Page 1 of 6 $~2 * IN THE HIGH COURT…
This page shows the compact analysis of this judgement. The full analysis — procedural history, issue-by-issue holdings with ratio and obiter, advocates, and paragraph-level evidence for every claim — is being added to the record in batches and will appear here when this judgement has been through it.
$~2
AZAD HIND COOP GROUP HOUSING SOCIETY LTD
..... Respondent
Through: Mr. P. S. Singh and Mr. Manu Arya, Advocates. % Date of Decision: 15th February, 2024
CORAM:
HON'BLE THE ACTING CHIEF JUSTICE HON'BLE MS. JUSTICE MANMEET PRITAM SINGH ARORA JUDGMENT
MANMOHAN, ACJ : (ORAL)
Signature Not Verified
Page 1 of 6
FAO(OS) 114/2017
Signed By:MAHIMA SHARMA Signing Da te:2 0.02.2024 11:27:15
months i.e., on or before 18th December, 1998. Subsequently, disputes arose between the parties on account of non-payment of Running Account (RA) Bills of the Appellant by the Respondent.
Submissions of counsel for parties
Signature Not Verified
Page 2 of 6
FAO(OS) 114/2017
Signed By:MAHIMA SHARMA Signing Da te:2 0.02.2024 11:27:15
Respondent for the work done by the Appellant i.e., Rs. 48,41,407/- and finally had deducted the amount spent by the Respondent on the said works at the risk of the Appellant i.e., Rs. 13,52,660/-. He states that this approach is a possible and a plausible view taken by the Arbitrator and did not warrant any interference much less setting aside of the Award to this extent. He states that the learned Single Judge could not have substituted the view taken by the Arbitrator with its own view. He states that the aforesaid method adopted by the Arbitrator reflects the reasons which weighed with it while passing the Award.
6.1. He states that it was not within the ambit of the Court to evaluate whether the view taken by the learned Arbitrator was justified on the evidence available on the record?
6.2. He states that the Court could not have looked into the reasonableness of the reasons recorded by the Arbitrator or disagreed with the reasons given in the Award. He states that the Court could not have set aside the Award on account of the reasoning therein being inadequate or imperfect.
6.3. He states that the findings of the learned Arbitrator while deciding counter claim no.1 to hold that the Respondent is entitled to claim a sum of Rs. 13,52,660/- from the Appellant towards the balance work carried out at its risk and costs has attained finality. He states that the findings on this counter claim have been upheld by the Court and consequentially no interference was merited with the Award passed in respect of issue numbers 1, 7 and 8.
Signature Not Verified
Page 3 of 6
FAO(OS) 114/2017
Signed By:MAHIMA SHARMA Signing Da te:2 0.02.2024 11:27:15
which the members of the Respondent Society suffered losses. He states that the members had to live in rented accommodations due to the noncompletion of flats in the project. He states that as per the MoU, the work executed by the Appellant had to be certified by the Architect and thereafter considered for payment. He states that the Architect certified work amounting to Rs. 41,98,805/- only. He states that the Project was abandoned by the Appellant and had to be completed by the Respondent Society at the risk and cost of the Appellant which caused further delays in completion. 7.1. He states that the Appellant was not entitled to the value of Rs. 32,33,593/-, for the unexecuted portion of the work awarded by the Arbitrator as there is no evidence on record that the Appellant completed the said work. He states that therefore, the Appellant was not entitled to any further payment as he had led no evidence to prove the execution of balance work before the Arbitrator.
Findings and analysis
Signature Not Verified
Page 4 of 6
FAO(OS) 114/2017
Signed By:MAHIMA SHARMA Signing Da te:2 0.02.2024 11:27:15
Rs.70,75,000/-, as against that he has been paid Rs.48,41,407/-. Thus, he would be entitled to the balance amount of Rs.22,33,593/- which will be subject to adjustment against the amount, if any, incurred by the respondent in purchase of material and for getting the work done at the risk of the claimant, if any. Order accordingly.”
Signature Not Verified
Page 5 of 6
FAO(OS) 114/2017
Signed By:MAHIMA SHARMA Signing Da te:2 0.02.2024 11:27:15
for the balance amount, the learned Arbitrator was obliged to return a finding based on evidence that indeed the Appellant had executed the works enlisted in Annexure - II of the MoU, entitling the Appellant to its claim, before awarding the differential amount of Rs. 32,33,593/-.
ACTING CHIEF JUSTICE
MANMEET PRITAM SINGH ARORA, J FEBRUARY 15, 2024/ msh/aa Click here to check corrigendum, if any
1Ssangyong Engg. & Construction Co. Ltd. v. NHAI, (2019) 15 SCC 131 Para 39 and Associate Builders v. DDA, (2015) 3 SCC 49 Para 42.2
Signature Not Verified
Page 6 of 6
FAO(OS) 114/2017
Signed By:MAHIMA SHARMA Signing Da te:2 0.02.2024 11:27:15
Colour shows how this judgement treated each authority
Ssangyong Engg. & Construction Co. Ltd. v. NHAIRelied on¶13
(2019) 15 SCC 131 · Who else cites this
Associate Builders v. DDARelied on¶13
(2015) 3 SCC 49 · Who else cites this
3 provisions across 1 enactments
M/S Harcharan Dass Gupta
Azad Hind Coop Group Housing Society Ltd
Manmohan
Manmeet Pritam Singh Arora
As recorded by the court registry
An appeal to a Division Bench against an order made by a single judge on the original side of the High Court.
Judgements on the same questions, provisions and authorities, from every court