Delhi Development Authority v. M/S Sanyukt Nirmata & Anr.
Case brief
What is this about?
This court set aside an arbitral award against Delhi Development Authority. It held that a contractual time-bar clause was valid and claims were time-barred. Additionally, claims for escalation and overheads were rejected because the arbitrator failed to apply the 10% threshold required by the contract.
What did the court decide?
The objections raised by the petitioner are allowed; the impugned award is set aside; no order as to costs.