Delhi Development Authority v. Cengers Geotechnica Pvt. Ltd.
Case brief
What is this about?
Registrar General listed to compute release of deposited amount. Respondent submitted calculation of Rs.13,38,813.45, while Standing Counsel sought time to file calculation pending further directions.
What the court decided
$~
- IN THE HIGH COURT OF DELHI AT NEW DELHI
- RFA 157/2017
DELHI DEVELOPMENT AUTHORITY ..... Appellant Through None
versus
CENGERS GEOTECHNICA PVT LTD ..... Respondent Through Mr. Lakshay Sharma, Adv. alongwith Mr. Sanjay Gupta, Managing Director of respondent
CORAM:
SH. DINESH KUMAR SHARMA, REGISTRAR GENERAL
O R D E R % 15.01.2019
Vide order dated 14.12.2018, the Hon’ble Court has inter alia directed as
under:-
“27. In the facts of this case, the interest shall run for the entire period @ 9% instead of the rate of interest awarded by thelearned ADJ. On 13th February, 2017, this Court had stayed the impugned judgment/decree subject to the DDA depositing in this Court and is lying in a fixed deposit. It is accordingly directed that the worthy Registrar General may release the sum of Rs.5,98,986/- along with interest @ 9% per annum w.e.f. 22nd July, 2005 till date. Any excess amount shall be refunded to the DDA. The demand draft be prepared within four weeks and be handed over to the Respondent through counsel in the presence of the Respondent’s authorised signatories.
Parties & counsel
- appellant
Delhi Development Authority
- respondent
Cengers Geotechnica Pvt Ltd
Coram
Dinesh Kumar Sharma
Case details
As recorded by the court registry
Similar cases
Judgements on the same questions, provisions and authorities, from every court