Chief Engineer, Public Works Department, National Highway Zone v. Itwari
Case brief
What is this about?
condonation of delay; 218 days delay; Section 5 Limitation Act; Section 37 Arbitration and Conciliation Act 1996; Section 34 set-aside proceedings; Section 3G(5) National Highways Act 1956; land acquisition compensation enhancement; National Highway No. 200 (New 49); sufficient cause; government department administrative delay not malafide; Borse Brothers (2021) 6 SCC 460; Sumitra Bai ARBA No. 62 of 2025; Ramlal v. Rewa Coalfields; High Court of Chhattisgarh; single judge; NAFR (not for reportable).
What did the court decide?
The appellant failed to demonstrate any sufficient cause for the 218-day delay; mere administrative and procedural circumstances (obtaining legal opinion, approvals, superannuation of the officer-in-charge, vacancy and winter vacation) do not constitute a satisfactory explanation for condonation of delay. ¶29