Chief Engineer v. Lokesh
Case brief
What is this about?
Condonation of delay; Section 5 Limitation Act; Section 37 Arbitration and Conciliation Act 1996; 248 days delay in filing arbitration appeal; PWD/government department delay grounds (legal opinion, approvals, superannuation of Executive Engineer, vacation); Borse Brothers (2021) 6 SCC 460 paras 62, 63, 68; delay beyond 90/30/60 days to be condoned by way of exception not rule; no vested right to condonation; Sumitra Bai ARBA No. 62 of 2025 (Chhattisgarh HC, 02.02.2026); National Highways Act 1956 Section 3G(5) enhancement of compensation; Section 34 application dismissed by District Court; arbitral award remanding matter to CALA; NH No. 200 (New 49) widening land acquisition; Janjgir-Champa; Bilaspur; ARBA No. 74 of 2025; appeal dismissed on limitation grounds alone.
What did the court decide?
None; I.A. No. 1 of 2025 for condonation of delay of 248 days was rejected and the arbitration appeal was dismissed on limitation grounds alone.