Veer Projects, Engineers and Contractor v. State of Chhattisgarh
Case brief
What is this about?
The court disposed of a writ petition regarding unpaid construction dues under the Pradhan Mantri Avas Yojna. Finding that roughly Rs. 1 crore remains undisputed and is under process, the court directed the Municipal Corporation to release the admitted dues within 90 days.
What did the court decide?
Direction to respondent No. 2 to ensure that the unpaid and admitted dues be released to the petitioner within 90 days.