Snehungshu Das v. State of West Bengal and Ors.
Case brief
What is this about?
This writ petition dealt with unauthorized construction obstructing the petitioner's ingress. Noting that proceedings under the West Bengal Highways Act, 1964 were already initiated, the Court directed the authority to conclude the proceedings within two months after a hearing.
What did the court decide?
Direction to the 4th respondent to conclude the proceedings under Section 10 of the West Bengal Highways Act, 1964 within two months after a hearing.