Executive Engineer, (Civil) Ehv Cccm Division - Msetcl and Ors. v. Mohan Narayan Mahajan and Ors.
Case brief
What is this about?
The High Court of Judicature at Bombay allowed two interim applications: one condoning delay (683 days) for filing a First Appeal, relying on liberal construction of Section 5 of the Limitation Act, and another seeking stay of execution. The First Appeal (ST) No. 14166/2021 concerning land acquisition for an MSEB sub-station was admitted, with contentions kept open.
What did the court decide?
Interim Application 14169/2021 for condonation of delay allowed; Interim Application 14170/2021 for stay allowed; First Appeal 14166/2021 admitted.