Contempt petition closed on compliance — Bombay High Court, Farhan P. Dubash, J., order dated 10 April 2026; CP 523/2025 in AFO 769/2024; Petitioner Sujita Narayan Nakhwa (Mr. Pradeep M. Havnur); Respondent Ravindra Baburao Patil; Respondent no. 2 MCGM (Mr. Anup Patil a/w Ms. Neeta Jadhav, i/b. Ms. Komal Punjabi); compliance report dated 6 March 2026 marked 'X'; demolition of construction violating order dated 18 November 2024; both Contempt Petition and Appeal From Order disposed of, no order as to costs; no statute or precedent cited or discussed.
What did the court decide?
No substantive relief; the Contempt Petition and the connected Appeal From Order were both disposed of with no order as to costs following the Corporation's compliance (demolition of the offending construction). ¶17