Rajeev Manmohan Gupta v. Brijwasi Builders
Case brief
What is this about?
Section 37 challenge to Section 17 interim order; Arbitration and Conciliation Act 1996; interim measures; security over constructed area; Joint Affidavit; retired partners; refund of capital contribution; partnership capital; Brijwasi Builders; illusory relief; no construction progress; liberty to approach arbitral tribunal; re-assessment of interlocutory measure; Bombay High Court Commercial Division; CARBP 15/2025; Somasekhar Sundaresan J.
What did the court decide?
No interference with the Impugned Order; liberty to the Petitioners to approach the learned Arbitral Tribunal to indicate that the relief envisaged in the Impugned Order has turned out to be illusory; Petition finally disposed of. ¶¶22