The Executive Engineer Seena Kolegaon Medium Project Paranda Osmanabad v. Bhimrao Krishna Bhandurge and Ors.
Case brief
What is this about?
Land acquisition compensation; delay condonation (315 and 288 days) in appeals FAST/15473/2024 and FAST/15477/2024; partial release of deposited compensation of Rs.10,48,261 - 75% with accrued interest against undertaking to Registrar (Judicial); balance invested in nationalized bank; ad-interim relief confirmed; acquiring body: Collector, Osmanabad; Bombay High Court, Aurangabad Bench; Shailesh P. Brahme, J.; 05.05.2026; citation 2026:BHC-AUG:20634.
What did the court decide?
Delay of 315 and 288 days in preferring the respective appeals condoned; applicant permitted partly to withdraw the deposited amount - 75% of Rs.10,48,261 with accrued interest on furnishing undertaking to the satisfaction of the Registrar (Judicial), balance to be invested in a nationalized bank; ad-interim relief confirmed; all civil applications disposed of.