Maharashtra State Electircity Transmission Company Ltd. Thr. Its Executive Engineer v. the State of Maharashtra the. Its Rural Development and Water Conservation Department and Ors.
Case brief
What is this about?
Bombay High Court stand-over order dated 1 April 2025 in WRIT PETITION NO. 14020 OF 2024, Maharashtra State Electricity Transmission Company Ltd. (MSETCL) v. The State of Maharashtra & Ors.; heard with Interim Application No. 13803 of 2024 and Writ Petition No. 15703 of 2024; Bench: A. S. Gadkari and Kamal Khata, JJ.; matter stood over to 24 June 2025 with continuation of any earlier ad-interim relief; Counsel: Kuldip T. Pawar (with Shahajirao Shinde) for petitioner; S.S. Bhende AGP for State; Sarang S. Aradhye for R-2 & R-3; Priyanka Chavan for R-4 & R-5; no merits adjudicated.
What did the court decide?
Purely procedural stand-over: matter adjourned to 24 June 2025, with ad-interim relief, if any granted earlier, to continue till the next date. No merits adjudicated. ¶19