Tushar Enterprise v. Dahisar Shree Awdhoot Chs Ltd.
Case brief
What is this about?
Bombay High Court interim order dated December 22, 2025 (Somasekhar Sundaresan, J.) in Interim Application Nos. 4043, 4051 and 4291 of 2025 in Suit No. 121 of 2024, Dahisar Shree Awdhoot CHS Ltd. v. Vimal Gopinath Mhatre & 4 Ors.: condonation of delay in filing written statement; costs of Rs. 5,000/- per application; Tushar Enterprise (Original Defendant No. 6); ad-interim arrangements continued; rejoinder of Original Plaintiff taken on record; IA No. 4291 of 2025 listed January 28, 2026; Ordinary Original Civil Jurisdiction; cooperative housing society suit; BMC and State respondents.
What did the court decide?
Delay in filing the Written Statement condoned for the Applicants in Interim Application Nos. 4043 and 4051 of 2025, subject to payment of costs of Rs. 5,000/- each within two weeks; Registry to accept the Written Statements upon demonstration of payment of costs; ad-interim arrangements continued until the next date; rejoinder of the Original Plaintiff taken on record; Interim Application No. 4291 of 2025 listed on January 28, 2026.