Shreeji Realtors (I) Pvt. Ltd. v. Patel Group
Case brief
What is this about?
Bombay High Court, O.O.C.J.; Interim Application No. 2482 of 2024 in Commercial Execution No. 22 of 2021; Shreeji Realtors (I) Pvt Ltd v. Patel Group & Co. and others; Abhay Ahuja, J.; order dated 30 July 2025; amendment of Schedule of Execution Application to include five additional immovable properties; opposed by Respondent No.4 on ownership grounds; reply by Respondent No.4 within two weeks; service on other Respondents within three weeks; rejoinders by next date; adjourned to 17 September 2025; purely procedural interlocutory order; no statutes or precedents cited; no substantive holding.
What did the court decide?
Application not decided; matter adjourned to 17 September 2025 with directions: Respondent No.4 to file reply within two weeks with a copy to the other side; service on the other Respondents to be effected within three weeks if not already effected; other Respondents to file replies within two weeks thereafter; rejoinders by the next date.