J H Construction Pvt. Ltd. v. Municipal Council Bhandara
Case brief
What is this about?
Extension of arbitrator's mandate under S.29-A(4)/(5) Arbitration and Conciliation Act 1996; 12-month period expired 03/04/2025; delay attributed to respondent Municipal Council, Bhandara failing to adduce evidence after claimant concluded evidence on 15/10/2024; substitution under S.29-A(6)/Ss.14-15 refused — no bias pleaded or made out, no failure to proceed expeditiously, no de jure/de facto incapacity, mandate not terminated; exhibited document not readable in evidence unless proved; W.P. 6670/2024 dismissal gave interlocutory order finality; Poonam Mittal 2024 SCC OnLine Del 6621 and Indiabulls Infraestate 2025 SCC OnLine Bom 1760 relied on; ACC Ltd v Global Cements (2012) 7 SCC 71 distinguished on facts; Hemendra Rasiklal Giha 2008(6) Mh.L.J 886 explained; mandate of Justice A.P. Deshpande (Retd.) extended six months from 02/08/2025; application allowed; costs rejected.