The Executive Engineer, Nimn Painganga Project Division (Bembla Project), Yavatmal v. Shri. Gajanan Devidas Tammewar and Others
Case brief
What is this about?
Deposit of awarded compensation with accrued interest permitted; civil application disposed of. Parties: The Executive Engineer, Nimn Painganga Project Division, Yavatmal (applicant/appellant) vs Gajanan Devidas Tammewar and Ors. (respondents); Ms. M.R. Kavidmandan, AGP for respondent/State; none for applicant. Court: High Court of Judicature at Bombay, Nagpur Bench. Judge: Abhay J. Mantri. Date: 13.06.2025. Case: CAF No. 2001 of 2025 in First Appeal (ST) No. 2458 of 2023. Deposit timeline: two weeks from the order.
What did the court decide?
Permission to deposit the awarded compensation amount, along with accrued interest thereon, into the Court within two weeks from today. ¶13