The Ex Engineer Mid Latur Now Lmid Under Gmidc Aurangabad and Others v. Balasaheb Ram Ganjewar
Case brief
What is this about?
Aurangabad Bench of the Bombay High Court (Shailesh P. Brahme, J., 09.06.2025) allows Civil Applications Nos. 2466 and 2468 of 2025 in FAST/1979/2025 filed by the Ex Engineer MID Latur (now LMID under GMIDC Aurangabad) seeking condonation of 270 days' delay in filing a first appeal against the judgment and award dated 02.12.2023 in favour of Balasaheb Ram Ganjewar; conditional protection granted: deposit of 60% of the amount within six weeks, claimant free to withdraw 50% of the deposit on undertaking, and automatic vacation of earlier ad-interim relief on default.
What did the court decide?
Delay of 270 days in preferring the first appeal condoned; civil application allowed in terms of prayer clause “B”; Office directed to register the first appeal and the appeal admitted; service of notice waived by counsel for respondent; Record and Proceedings to be called from the concerned Court; time extended by six weeks to deposit 60% of the amount as directed earlier, failing which the ad-interim relief granted earlier stands vacated automatically; respondent/claimant permitted to withdraw 50% of the deposited amount on furnishing undertaking to the satisfaction of the Registrar (Judicial).