Cable Corporation of India Limited v. the Western Edge II Premises Co-Operative Society Limited Thr. Authorized Mr. Nitin Kajalkar
Case brief
What is this about?
Cable Corporation of India Limited v. The Western Edge II Premises Co-operative Society Limited; Appeal From Order No. 14 of 2024; Interim Application No. 241 of 2024; Bombay High Court; Gauri Godse, J.; 4 February 2025; appeal admitted; temporary injunction in terms of final reliefs; restrictions on original owner utilizing FSI; flat purchase agreement clause 34 conveyance from developer; development agreement FSI inclusive of TDR limited to 59,157 square meters on 31,323 square meters; prima facie no relief beyond developer's entitlement; ad-interim stay prayer clause (a); rule returnable 1st April 2025.
What did the court decide?
Appeal admitted as raising arguable points; Rule on interim relief in terms of prayer clause (a) made returnable on 1st April 2025; ad-interim stay granted in terms of prayer clause (a) of Interim Application No. 241 of 2024 during the pendency of the application.