Deena Pramod Baldota v. Chief Executive Officer (C.E.O)
Case brief
What is this about?
Limitation for appeal under Section 17(6) of Maharashtra Slum Areas (Improvement, Clearance and Redevelopment) Act, 1971; whether thirty-day period runs from Competent Authority's objection notice dated 10 February 2023 or final compensation-determination order dated 8 August 2023; construction of 'notice' under Section 17(5); notice for hearing vs determination; appeal dismissed as time-barred; quashing of Appellate Tribunal order dated 10 July 2024 and restoration of appeal; Slum Rehabilitation Authority compensation determination; writ petition under Article 226; Bombay High Court, Kamal Khata, J.; WP 1014 of 2025; Deena Pramod Baldota.
What did the court decide?
The impugned Order dated 10th July, 2024 is quashed and set aside; the Appeal is restored on the file of the Maharashtra Slum Areas Tribunal and Special Tribunal, Mumbai, for adjudication on merits in accordance with law; no order as to costs.