Nanded City Development and Construction Company Ltd. v. Sunil Champalal Somani and Ors.
Case brief
What is this about?
Writ petitions challenged District Court orders extending the arbitrator's mandate under Section 29-A, contending only the appointing Court holds that power. Following an identical Bombay High Court decision, the impugned orders were quashed, the applications treated as made before this Court, and the mandate extended by twelve months.
What did the court decide?
Impugned District Court orders dated 07.12.2023 quashed; Civil Misc. Applications treated as before this Court and allowed; arbitration mandate extended by further 12 months.