Occupancy and building completion certificates were withheld because a sanctioned building obstructed a proposed ring road. The court held that acquisition and approved development proposals varied the regional plan, and directed conditional issuance within three months. The landowner's separate challenge to proposed realignment was disposed of as its cause did not survive.
What did the court decide?
MIDC directed to grant occupancy and building completion certificates within three months, subject to conformity with sanctioned plans and completion of legal formalities.