Shivaji Anantrao Kulkarni v. the State of Maharashtra and Others
Case brief
What is this about?
This PIL raised a grievance regarding the delay in constructing a specific 15-meter road stretch. The respondent municipal corporation explained that the earlier order was cancelled due to budget shortages but submitted new administrative approvals dated May 2017 and February 2018 for the road construction. The High Court accepted these submissions, found the grievance addressed, and disposed of t
What did the court decide?
The grievance was addressed by evidence of fresh administrative approvals; the suit filed as PIL is dismissed.