Rna Corp Pvt. Ltd. v. Rna Viva Residents Association
Case brief
What is this about?
The Bombay HC disposed of appeals against a Court Receiver appointment and sought extension. The Court accepted the appellant's undertaking to complete construction by new dates and cure defects within stipulated timelines, refusing any further extension.
What did the court decide?
Extension of time for Project Phase I to 15/03/2019 and Phase II to 31/10/2019 granted subject to strict undertakings for completion and no further extension; Appeals disposed.