Rna Corp Pvt. Ltd. v. Rna Viva Residents Association
Case brief
What is this about?
The bench disposed of appeals and related motions regarding a rental agreement suit involving construction delays. The court accepted the appellant's undertakings and jointly agreed modalities, granting a final extension of time for project completion contingent upon strict adherence and appointment of an independent contractor in case of breach.
What did the court decide?
Extensions of time granted for Phase I (till 15 March 2019) and Phase II (till 31 October 2019) subject to undertaking; Court Receiver appointed to take possession on breach.