Rna Corp Pvt. Ltd. v. Rna Viva Residents Association
Case brief
What is this about?
In an appeal arising from a project completion dispute, the High Court, Bombay accepted the Appellant's unconditional undertakings regarding timelines and jurisdiction waivers. The Court granted final extensions for two construction phases, stipulated strict consequences including immediate receiver takeover upon default, and disposed of related motions without recording detailed reasons, adhering
What did the court decide?
Extensions granted: Phase I to 15/3/19; Phase II to 31/10/19. Undertakings accepted barring further extensions and jurisdiction claims. Disposal ordered based on agreed modalities.