State of Goa through Chief Secretary and Anr., v. C. M. Abdul Khader
Case brief
What is this about?
A road contractor sought compensation for delayed works, extra excavation and disputed deductions. The court partly allowed the contractor's appeal, awarded consolidated idling compensation and directed interest from institution of the suit. It rejected enhanced excavation rates and other additional claims, and dismissed the defendants' appeal.
What did the court decide?
Additional consolidated idling compensation; interest at 6% per annum from institution of the suit on that compensation and the amounts already awarded.