Shri. C. M. Abdul Khadar v. State of Goa Represented by Chief Secretary and Anr.
Case brief
What is this about?
Cross appeals from a decree in a PWD contractor's suit for breach of a road-widening contract. The court held the defendants responsible for about ten months' delay, refused the claim for extra excavation at GSR/market rates, upheld refunds of wrongful recoveries, and dismissed the State's appeal while partly allowing the contractor's appeal.
What did the court decide?
First Appeal No.232/2008 dismissed; First Appeal No.116/2008 partly allowed, with interest at 6% p.a. from the date of the suit on the decreed amounts, and Rs.25 lakhs with like interest for idling ch