Firoz Khan Shabbir Khan and Anr. v. State of Maharashtra through Principal Secretary Dept. of Housing and Urban Development and 2 Ors.
Case brief
What is this about?
The Court allowed the writ petition challenging a demolition notice while keeping the issue of rehabilitation eligibility pending before the appellate authority. It directed the Municipal Corporation to measure structures on a specific date to ascertain distance from the Tansa pipeline and decided the appeals within eight weeks, interlinking demolition action with eligibility findings.
What did the court decide?
Court directed Municipal Corporation to measure structures on 17.02.2018 and decide appeals within 8 weeks. Demolition actionable only if structures found within 10 meters or post-eligibility determin