Ganpat Gangaram Ingale and Another v. Maharashtra State Electricity Transmission Company Limited, (M.S.E.T.C.L) Thr. Chief Engineer
Case brief
What is this about?
The High Court disposed of the Writ Petition on the ground that the petition was filed at a belated stage regarding transmission towers erected in 1995. The Court directed the petitioners to seek compensation from the concerned authority. No opinion on the merits was expressed.
What did the court decide?
Petitioners directed to approach the concerned authority for compensation within one month; respondent to decide within two months. Petition disposed.