Horizon Flora India Ltd. v. Asset Reconstruction Co. (I) Ltd.
Case brief
What is this about?
IN THE HIGH COURT OF JUDICATURE AT BOMBAY…
This page shows the compact analysis of this judgement. The full analysis — procedural history, issue-by-issue holdings with ratio and obiter, advocates, and paragraph-level evidence for every claim — is being added to the record in batches and will appear here when this judgement has been through it.
1
NM2381-10=15.9
PNP
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
ORDINARY ORIGINAL CIVIL JURISDICTION
NOTICE OF MOTION NO.2381 OF 2010 IN APPEAL (LODG.) NO.559 OF 2010 IN COMPANY PETITION NO.189 OF 2008
Horizon Flora India Limited Vs.
Asset Reconstruction Co.(I) Ltd.
..Appellant.
..Respondent.
Mr. Sachin Punde for the Appellant. Mr. Sahil Saiyed i/b Apex Law Partners for the Respondent.
CORAM : MOHIT S. SHAH, C. J. & DR. D.Y.CHANDRACHUD, J.
15 September 2010.
P.C . :
We have heard learned counsel appearing for the parties. We find that sufficient cause is shown for the delay of six days in filing the Appeal. Hence, the delay is condoned. The Notice of Motion is allowed.
The Appeal shall be listed before the appropriate Bench on 23 September 2010.
CHIEF JUSTICE
(DR. D.Y.CHANDRACHUD, J.)
Horizon Flora India Limited
Asset Reconstruction Co.(I) Ltd.
MOHIT S. SHAH
DR. D.Y.CHANDRACHUD
As recorded by the court registry
Judgements on the same questions, provisions and authorities, from every court