Reliance Infrastructure Limited and 2 Ors. v. Maharashtra State Road Development Corporation Limited and Anr.
Case brief
What is this about?
In WP 1542 of 2009, a writ petition was dismissed but the Court granted a limited stay pending three weeks to enable the petitioner to comply with the law, ordering the third respondent to pay Rs.2100 crores within the contractual period.
What did the court decide?
Limited stay granted for three weeks; third respondent must pay Rs. 2100 crores after issuing an acceptance letter.