FPA-PMLA-2998/JP/2019 of M/s Charlie Tradelink Pvt. Ltd. v/s The Joint Director Directorate of Enforcement, Jaipur
Case brief
What is this about?
M/s Charlie Tradelink Pvt. Ltd. V/s The…
This page shows the compact analysis of this judgement. The full analysis — procedural history, issue-by-issue holdings with ratio and obiter, advocates, and paragraph-level evidence for every claim — is being added to the record in batches and will appear here when this judgement has been through it.
APPELLATE TRIBUNAL FOR SAFEMA, FEMA, PMLA, NDPS & PBPT ACT AT NEW DELHI
MP-PMLA-5950/JP/2019 (Stay) MP-PMLA-55951/JP/2019 (COD) MP-PMLA-5952/JP/2019 (Exem.) FPA-PMLA-2998/JP/2019
M/s Charlie Tradelink Pvt. Ltd. … Appellant
Versus The Joint Director Directorate of Enforcement, Jaipur … Respondent
Advocates/Authorized Representatives who appeared
| For the appellant | : Dr. Shamshuddin , Advocate |
|---|---|
| For the respondent | : Shri Neeraj Atri, Advocate |
| CORAM | |
| JUSTICE MANMOHAN SINGH SHRI G.C. MISHRA |
: CHAIRMAN : MEMBER |
| 1 | ORDER 6.07.2019 |
FPA-PMLA-2998/JP/2019 & MP-PMLA-55951/JP/2019 (COD)
Reply to the application for condonation of delay has been filed. On 30th May, 2019, the respondent seeks time to take the instruction as to whether prosecution complaint in the said matter has been filed or not. He is unable to get the instruction. He seeks more time to take the instruction.
As far as condontion of delay application is concerned, reply as been filed. There is a controversy remains as to whether the appellant was served with the impugned order or not. Counsel for the appellant states that no copy was served and whenthe appellant came to know
FPA-PMLA-2998/JP/2019,
Page 1 of 2
about the said order, the application for certified copy was filed. According to the appellant, the appeal is within the time.
We have to check up the record of the Adjudicating Authority. The Adjudication Authority’s registry is directed to provide us proof/record in order to show as to whether the impugned order was served/delivered.
Let the same be done within 10 days. Registry is also directed to
take necessary steps in this regard immediately.
List on 8th August, 2019.
(Justice Manmohan Singh) Chairman
(G.C. Mishra) Member
New Delhi, 16th July, 2019 ‘s’
FPA-PMLA-2998/JP/2019,
Page 2 of 2
M/s Charlie Tradelink Pvt. Ltd.
The Joint Director Directorate of Enforcement, Jaipur
MANMOHAN SINGH
G.C. MISHRA
As recorded by the court registry
14 orders share this CNR
Judgements on the same questions, provisions and authorities, from every court