FPA-FE-1064/BNG/2004 of Shri K. Mohd. Imran v/s The Joint Director, Directorate of Enforcement, Bangalore
Case brief
What is this about?
Shri K. Mohd. Imran V/s The Joint Director…
What did the court decide?
Appellant granted four weeks time to comply with an order dated 01.05.2019.
What the court decided
APPELLATE TRIBUNAL FOR SAFEMA, FEMA, NDPS, PMLA & PBPT ACT AT NEW DELHI
FPA-FE-1064/BNG/2004 Shri K. Mohd. Imran … Appellant
Versus
The Joint Director, Directorate of Enforcement, Bangalore … Respondent
Advocates/Authorized Representatives who appeared
| For the appellant | : Ms. Rachna Chillar, Advocate Shri Tarun Singh Awana, Advocate |
|---|---|
| For the respondent | : Mrs. Aagam Kaur, Legal Consultant |
| CORAM | |
| SHRI G.C. MISHRA | : ACTING CHAIRMAN |
| ORDER 16.10.2019 |
FPA-FE-1064/BNG/2004
Learned counsel for the appellant is present. Mrs. Aagam Kaur, Legal Consultant for the respondent is also present. The appellant is to comply the order dated 01.05.2019. Learned counsel for the appellant seeks four weeks time to comply the said order i.e. filing of the copy of the writ petition as well as the order passed by the Hon’ble Delhi High Court. Let the copy of the same be served on the other side. Further order would be passed only after going through the copy of the Hon’ble Delhi High Court.
Parties & counsel
- appellant
Shri K. Mohd. Imran
- respondent
The Joint Director, Directorate of Enforcement
Coram
G.C. Mishra
Case details
As recorded by the court registry
All orders in this case
13 orders share this CNR
Similar cases
Judgements on the same questions, provisions and authorities, from every court