FPA-PMLA-2186/GOA/2018 of M/s Navdeep Agriculture & Properties Pvt. Ltd. v/s The Joint Director Directorate of Enforcement, Goa
Case brief
What is this about?
This order condones a 25-day delay in filing appeals under Section 26 of the PMLA, 2002, requiring a penalty payment. It directs the issuance of notice to the respondent with a limit to file a reply within six weeks and lists the matter for further hearing.
What did the court decide?
Delay condoned subject to payment of Rs. 2,000; notice issued to respondent; reply required within six weeks; matter listed for 18th July 2018.