Appeal No. 259 of 2017 & Ia No. 718 of 2024 of Gama Infraprop (P) Ltd. v. Uttarakhand Electricity Regulatory Commission & Anr.
Case brief
What is this about?
The Appellate Tribunal for Electricity allowed the appeal, setting aside the State Commission's disallowance of interest during construction for delays caused by gas unavailability. It directed a usage-based reallocation of capital costs instead of a 50:50 split and allowed pre-operative expenses and carrying costs.
What did the court decide?
Set aside disallowance of IDC, pre-operative expenses, and hard costs; direct the State Commission to reallocate capital costs based on usage and allow carrying costs on the admissible amounts.