Appeal No.235 of 2022 of Guttaseema Wind Energy Company Private Limited v. A.P. State Electricity Regulatory Commission & Anr.
Case brief
What is this about?
The Tribunal examined the interpretation of the Commercial Operation Date (COD) clause in a Power Purchase Agreement between a wind energy company and a distribution licensee. The Commission had held that the full two-year timeline from the agreement date applied to the entire project, ignoring an explanation stating the first unit's synchronization marks the COD. The Tribunal ruled that the expla
What did the court decide?
The impugned order was set aside, the termination notice was quashed, the project was deemed commissioned within the stipulated period based on the first unit's synchronization, and the licensee was d