Appeal No. 184 of 2023 of M/s Renew Clean Energy Private Limited v. Madhya Pradesh Electricity Regulatory Commission & Anr.
Case brief
What is this about?
The Tribunal allowed an appeal by a power producer against the Electricity Regulatory Commission's order. The Court held that the Commission cannot restrict compensation for GST-induced 'Change in Law' events to costs incurred only up to the project's commissioning date. It ruled that O&M costs via outsourcing are recoverable and carrying cost is inherent in the concept of 'relief'.
What did the court decide?
The impugned order of the Commission is set aside. The Commission is directed to pass consequential orders allowing compensation for additional expenditure post-SCOD, O&M costs, and carrying cost.