A.No. 359 of 2019 of Power Grid Corporation of India Limited. v. Central Electricity Regulatory Commission. & Ors.
Case brief
What is this about?
Appeal against CERC order disallowing IDC/IEDC due to uncondoned time overrun in commissioning transmission assets. Tribunal found inconsistency in CERC's approach to commissioning delays and similar past orders. Issue remitted to CERC for consistent reconsideration.
What did the court decide?
Set aside the impugned order; matter remitted to Central Commission for consistent reconsideration of issues regarding time overrun, crediting syndicated IDC/IEDC, and confirmation of Commercial Opera