A.Nos. 23 of 2020 and 278 of 2021 of Avaada Energy Private Limited. v. Central Electricity Regulatory Commission. & Ors.
Case brief
What is this about?
The Tribunal upheld the CERC order recognizing 28 MW of a solar project as commissioned, set aside rescission of the PPA and PSA, and directed SECI to pay the tariff. It held that termination was unjustified due to unavoidable government-related delays and affirmed the validity of the 28 MW capacity.
What did the court decide?
The CERC order dated 17.12.2018 is upheld; PPA and PSA termination set aside; SECI/MSEDCL to pay tariff for 28 MW; 6.48 crores returned.