A.No. 182 of 2022 of M/S Ascent Hydro Projects Limited & Ors. v. Madhya Pradesh Electricity Regulatory Commission. & Ors.
Case brief
What is this about?
This appeal challenges the dismissal of the appellants' claim for exemption from Cross Subsidy Surcharge and the continuation of a 2% wheeling charge cap. The Tribunal held that since the appellants commenced operations after the Electricity Act, 2003, previous exemptions and orders were inapplicable. The appeal was dismissed.
What did the court decide?
The appeal was dismissed; claim for Cross Subsidy Surcharge exemption and continued 2% wheeling charges rejected.