What is this about?
SVR Constructions v. State of A.P. and Kakinada Municipal Corporation; W.P. No. 8868/2026 (IA No. 1 of 2026); High Court of Andhra Pradesh at Amaravati; Justice Harinath.N; decided 07.07.2026. Contractor payment dispute: withholding/release of pending bills of Rs. 73,38,532/- for cc drains and cc roads works, Agreement No.10/EE-1/2023-24 dated 29.08.2023, 8th Division Kakinada; M-Book recording; bills approved, Government funds awaited; Article 226 Mandamus; Article 21 invoked; Section 151 CPC interim petition; disposed at admission stage with direction to verify and release payments within six weeks; no costs; interest @ 24% p.a. claimed but not dealt with. No precedents cited.
What did the court decide?
Respondents directed to verify and release the payments due and payable to the petitioner as expeditiously as possible, preferably within six (06) weeks from receipt of a copy of the order; no order as to costs; pending miscellaneous petitions, if any, stand closed. The prayer for interest @ 24% per annum is not addressed in the order.