Progressive Engineering Enterprises v. Union of India
Case brief
What is this about?
Keywords: tender rejection; technical bid; bid security; bank guarantee validity shortfall; non-responsive bid; essential eligibility condition; post-bid modification prohibited; reverse auction (e-RA); Clause 6 Annexure-I Tender Form; railway procurement, East Coast Railway, Waltair Division; Article 226 judicial review restraint in contractual/commercial matters; Tata Motors v. BEST (2023) 19 SCC 1 relied on; Silppi Constructions (2020) 16 SCC 489 referred; Hytronics Enterprises (Telangana HC, W.P.No.25868 of 2023) distinguished; writ petition dismissed, no costs. Relevant to public procurement disputes over defective bid securities and the limits of writ interference with tender decisions.
What did the court decide?
Since the tender validity ran up to 01.03.2026, the bid security had to be valid up to 30.05.2026; the petitioner's B.G. valid only till 19.05.2026 fell short of the mandatory validity period, amounting to a patent non-compliance of an essential requirement that renders the bid inherently defective and non-responsive.