Parameswari Power Projects Pvt. Ltd., v. The Employees Provident Fund Organization
Case brief
What is this about?
Parameswari Power Projects Pvt Ltd v Employees Provident Fund Organization and Recovery Officer, Guntur; WP 22712/2015; Article 226 mandamus against EPFO 7A determination order dated 09.06.2015 (GR/GNT/57984/Comp-I/K-I/7A Order/2015/312) directing PF dues payment through ECR; writ petition closed without merits decision on 02.03.2026 following demise of Managing Director R.V.S.R.K. Sharma (30.09.2025); no orders as to costs; pending miscellaneous applications (IA No.1 of 2015/WPMP 29342 of 2015; IA No.4 of 2015/WPMP 128466 of 2015, Section 151 CPC) closed; Judge K. Sreenivasa Reddy; Andhra Pradesh High Court, Amaravati; no precedent cited.
What did the court decide?
None; the writ petition was closed on counsel's submission that no orders were necessary, without adjudicating the challenge to the 7A order, and with no order as to costs.